Building update: first contours visible, delivery materials, paintwork 4th floor Heymansgebouw

Contours Heymans Building
Contours Heymans Building

The first contours of the new building on the Heymans building are visible. This week the contractor placed the first two niches. These niches are characteristic for the garden-oriented design.

Update:

  • 26 June: supply of walls (nuisance on parking lot)
  • 27+28 June: drilling work between 7 and 9 a.m.

Inside the Heymans building

  • June 24th: painter starts work in stairwell on 4th floor Heymansgebouw

Heyman's Wing

  • Next week the new meeting rooms on the 3rd and 4th floor will be delivered by the contractor.

Planning coming weeks

  • From week 27 onwards, work will take place on the roof of the Ambulatorium and the Nieuwenhuis building.
  • From week 27, two rooms in the Munting will be rebuilt: M.0164 (at the lecture halls) and M.0228 (examination rooms). Both rooms will be split up and provided with an extra door.
  • In the 'construction industry holiday', construction work will come to a standstill. (29 July - 18 August)