Construction update 30 August: Monday 2 September concrete pouring, 4 to 6 September ramp Ambulatorium closed

Heymansbuilding

The contractor is only expecting extra construction nuisance on Monday morning 2 September because of the concrete pouring of the floors.

Ambulatorium

From 4 to 6 September, work will be carried out on the ramp at the Ambulatorium. The front door of the Ambulatorium will be closed during this work. The Ambulatorium and the offices on the first floor are accessible via the footbridge of the Nieuwenhuis building (via ALC).