First foundation pile for new Data centre UG into the ground
On Friday 18 September 2020 the construction of the new data center for the University of Groningen started at the Zernike Campus Groningen.
In a week's time 61 foundation piles will go down to a depth of 21 meters. To reduce noise and vibration nuisance, the foundation piles (so-called 'continious flight auger CFA) piles') will be screwed.
Planning
Construction started in September 2020. The data centre is expected to be in use early 2022. ENGIE (together with their partners Bouwgroep Dijkstra Draisma, advisor Zentrys, Dijkhuis ingenieurs and Team4architecten) will be responsible for the entire realization of the data centre. In addition, installation technical advisor Deerns will assist the university during the tendering, design and implementation phase.
Last modified: | 15 January 2021 4.26 p.m. |
More news
-
02 July 2025
Relinde Weil reappointed as a member of the Supervisory Board UG
The Minister of Education has reappointed Relinde Weil for a second term as a member of the Supervisory Board of the University of Groningen.
-
01 July 2025
Khalaf Alkhalaf elected Alumnus of the Year 2025
Khalaf Alkhalaf has been elected Alumnus of the Year 2025 by the University of Groningen. He has received the award for his commitment to providing good care and guidance to refugees in the Netherlands and the inspiring way in which he shares his...