Schedule

Schedule and phases of new Feringa Building
Schedule and phases of new Feringa Building

The construction of the Feringa Building will proceed in phases:

Phase 1a | Sections 5614, 5615 en 5616

Building sections 5614, 5615 and 5616 will be the first to be completed. Relocation will start as of September 2023.

Moving
Staff from buildings 5117 and 5118 of Nijenborgh 4 are the first into Feringa Building.

Demolition of building 5117 and 5118
Demolition of buildings 5117 and 5118 can start after the relocation of staff from buildings 5117 and 5118.

Phase 1b | Sections 5612 and 5613

Relocation to building sections 5612 and 5613 will start in December 2023.

Phase 2 | Sections 5611

As soon as building 18 is demolished, the construction of building section 5611 can be started.

More details about the construction and relocation planning will follow later.

Green park

Then all old buildings will be demolished. A green park will be created in front of the building.